Phase 05 – Electric, pluming, drywall, cabinet

Kitchen and Bathroom Cabinets, Cabinet Knobs and Countertop

Venting Microwave

All Electrical Items: Cable, Phone, Structured Wiring, Intercom System, Recessed Can Lights, Eyeball Lights, Coach Lights,

Appliance installation Upgrade 

Interior Color

Molding on the ceiling

Tails in wet area

Outside brick wall 3 color pattern


Week 21

At the beginning of the week, the dry wall panels were delivered  to the house. Within three days, the workers installed all the dry wall panels in the whole house including the ceiling.  Next week they will start filling in the gaps and covering the screw heads.

Week 22

This week they started filling in the gaps and covering the screw heads. Furthermore, they started to install the molding at the ceiling, also the doors has been installed in the inside of the house. The bricks, the sand and the cement for the facade has been arrived as well at the end of this week.

Week 23

This week they made huge progress on the inside of the house, they finished installing the molding on the ceiling, painted the walls and started to built in the kitchen cabinets as well as the sink in the bathroom. Next week they will start with the outside brick wall.

Week 24

Finally the brick wall has been finished and the tails in the bathrooms are installed. Furthermore the Microwave has been installed as well as some light on the outside of the garage. The brick pattern turned out beautiful, we are both very happy about the pattern we have chosen.